Question: 1 / 200

What is a punch list?

A system for collecting accurate field information for a contract status report

A list of items that must be completed prior to contract completion

A punch list is a crucial document in the construction process that outlines items that need to be completed or corrected before a project can be considered finished. It typically includes tasks that are either incomplete or do not meet the project's specifications and standards.

This list is often created during a walkthrough of the project as it nears completion and serves as a guide for the contractor and subcontractors to ensure that all aspects of the project fulfill the required quality and details outlined in the construction documents. Addressing each item on the punch list is a necessary step before the final payment is made and the project is officially closed.

In terms of the other options, some serve different purposes in the construction workflow. For instance, collecting field information for contract status reports is important for tracking progress, logging machine hours helps with equipment management and cost tracking, and a stencil for punching holes in steel is a tool that serves a very specific function in material fabrication. These tasks are integral to different phases of construction management but do not align with the concept of a punch list.

A form used for logging machine hours worked

A stencil for punching holes in steel