What does the term 'design/build' refer to?

  1. Fast-track construction is not allowed

  2. The owner is heavily involved

  3. One company is responsible for both design and construction

  4. No communication is allowed between the designers and construction professionals

The correct answer is: One company is responsible for both design and construction

The term 'design/build' refers specifically to a project delivery method in which a single entity is responsible for both the design and the construction of a project. This integrated approach allows for better coordination and collaboration between the design and construction teams, leading to more efficient project delivery and often cost savings for the owner. In this model, the owner contracts directly with one company, which can streamline decision-making processes and reduce the potential for misunderstandings that might arise when multiple parties are involved. This arrangement contrasts with traditional methods where the design and construction phases are handled by separate entities, potentially leading to conflicts or delays. The importance of this approach lies in its ability to enhance communication and collaboration, resulting in a more cohesive project execution. By having one company oversee both aspects, the project can benefit from a unified vision and a smoother workflow from inception to completion.