During which project phase is the owner's involvement the highest?

  1. Procurement

  2. Concept and feasibility

  3. Engineering and design

  4. Construction

The correct answer is: Concept and feasibility

The concept and feasibility phase is where the owner's involvement is the highest because this stage focuses on defining the project's goals, requirements, and overall scope. During this phase, the owner actively participates in discussions that shape the vision of the project, evaluates possible alternatives, sets budgets, and assesses the feasibility of different approaches. It is a critical time for gathering input and ensuring that the plans align with the owner’s expectations and objectives. Engagement during this phase lays the groundwork for the entire project and involves thorough decision-making that can significantly influence subsequent stages. In the procurement, engineering and design, and construction phases, while the owner still plays a role, those phases are typically more technical, with project managers, engineers, and contractors taking on more responsibility for the specifics and implementation of the project plans. Thus, the owner's highest level of involvement is distinctly found in the concept and feasibility phase.